SELECT A MENU OPTION!!
 
Mackay
Rockhampton Courthouse

The rectification of 12 years of leaking water into the office space below.

Danlaid Contracting Mackay was contacted by Geoff Murphy  from JM Kelly in Rockhampton and asked us if we could install a waterproofing system that would prevent moisture leakage which had been prevalent for the 12 previous years. We took on the project which entailed ripping up the 60mm  screed and tiles which was covering  the troublesome substrate. We then proceeded to install a new system which was the 4mm Testudo torch on membrane. Once that stage was completed we covered the membrane with 3mm  Coreflute protector board prior to the new screed being poured. On completion we also did a flood test which proved that our system was a success.